Home Forest North Drainage Project
Forest North Drainage Project
April 2017 Update - Drainage Project Print
Friday, 10 March 2017 17:48

The April 2017 Update for the status of the Forest North Drainage Project has been posted to the roadbond website.  Click on April 2017 Update for a pdf of the report, including a map of the current work area.

DeNucci Constructors, LLC continues work in the Braeburn Zone only. Asphalt patching for both the Sherbrooke and Braeburn Zones should start upon the completion of work in the Braeburn Zone. Concrete driveway replacement work continues in the Braeburn Zone. The Stillforest Zone is the next zone in line to begin work. All residents affected with the upcoming work have received notification. DeNucci should start water line relocation within two weeks in the Stillforest Zone. Residents can expect intermittent lane closures with flaggers on Broadmeade.

 
February 2017 Update - Drainage Project Print
Thursday, 09 February 2017 09:48

February 2017 Update Report for the Forest North Drainage Project.

 
Drainage Project - January 2017 Update Print
Friday, 06 January 2017 16:18

The January 2017 Update for the Forest North Drainage Improvement Project has posted.  For more information, contact the Public Involvement Team by calling (512) 943-1195 or emailing This e-mail address is being protected from spambots. You need JavaScript enabled to view it .

All project materials and updates, including any lane or road closures, will be posted on the Forest North Drainage Improvement Project page of the Road Bond website. We encourage you to sign up for news and updates under the “Subscriptions” tab. Forest North Drainage Improvement Project web link: www.roadbond.org/forestnorth

 
Drainage Project - November 2016 Update Print
Monday, 05 December 2016 21:28

DeNucci Constructors, LLC continues work in the Tichester and Sherbrooke zones. Storm pipe installation along Sherbrooke Street has been completed; storm pipe installation along Broadmeade Street has also begun. Asphalt patches for utility trenches on Meadowheath Drive and Briar Hollow Drive have been completed. Concrete aprons around area drainage inlets along Sherbrooke Street have been formed and poured. Water line installation at the Sherbrooke and Broadmeade intersection in the Sherbrooke Zone continues. Water line installation at the Broadmeade and Meadowheath intersection continues; installation of the water line at this intersection is expected to continue over the next two weeks. Water line work at the intersection of Broadmeade and Sherbourne is expected to begin in two weeks, as well.

 

The Tichester (yellow) and Sherbrooke (green) zones are highlighted in the image below. A larger map of the neighborhood and the work zones can be found here.


Members of the construction team will continue to make door-to-door visits prior to actual construction in each zone. Vehicles parked on the street may need to be relocated while work occurs. Please, continue to visit the project website for updates.

 

Utility Relocations

AT&T relocations are ongoing in the Braeburn, Wisterwood and Briar Hollow zones.  Crews have completed placement of new lines in the existing easements, and will be splicing them into the existing system.

 

Tichester and Sherbrooke Zone Residents:

Residents in the construction area have received notifications about the project and a door hanger regarding homeowner items in the right-of-way. If you wish to preserve these items (custom mailboxes, landscaping, planters, trees, irrigation systems, etc.), it is suggested you begin removing them now from the right-of-way. If homeowner items are not removed by the time construction begins, then the contractor will consider these items left for refuse.

 

Mailboxes: Mailboxes in the path of drainage work will be removed and replaced with standard units. We are in close communication with the post office to ensure there is no disruption of mail service.

 

Driveways: The re-grading of channels and replacement of driveway culverts will require the re-construction of some driveways. Driveways will be accessible by the end of each workday. Full driveway repairs will be made upon completion of the entirety of the work at each property. Notice will be provided to homeowners and residents at least 48 hours prior to any driveway-access interruptions.

 

Irrigation Systems: Irrigation systems in the path of drainage work will be removed, capped at the right-of-way line and will not be replaced.

 

Questions, Subscribe to Email Alerts and Project Webpage

If you have any questions regarding this information, please contact our Public Involvement Team by calling (512) 943-1195 or emailing This e-mail address is being protected from spambots. You need JavaScript enabled to view it . All project materials and updates, including any lane or road closures, will be posted on the Forest North Drainage Improvement Project page of the Road Bond website. We encourage you to sign up for news and updates under the “Subscriptions” tab.

Forest North Drainage Improvement Project web link: www.roadbond.org/forestnorth.

 

Sincerely,

The Williamson County Public Involvement Team

Phone: (512) 943-1195

Email:  This e-mail address is being protected from spambots. You need JavaScript enabled to view it

 

 
Drainage Project - October 2016 Print
Tuesday, 25 October 2016 15:31

Forest North Drainage Improvement Project - Update Received October 25, 2016

DeNucci Constructors, LLC continues work in the Tichester and Sherbrooke zones. Water line relocation continues at the Meadowheath Drive /Sherbrooke Street intersection with a scheduled completion in two weeks. Pipe installation and rock excavation for storm sewers in the Sherbrooke zone continues along Sherbrooke Street and Meadowheath Drive. Asphalt repairs have begun on Meadowheath Drive and Briar Hollow Drive and completion is anticipated in two weeks. Seeding and installing an erosion control blanket along Meadowheath Drive, Haversham Court and Briar Hollow Drive is expected to begin in two weeks.

The Tichester (yellow) and Sherbrooke (green) zones are highlighted in the image below.  A larger map of the neighborhood and the work zones can be found here.


 

Members of the construction team have made or will make door-to-door visits prior to actual construction in each zone.  Vehicles parked on the street may need to be relocated while work occurs. Please, continue to visit the project website for updates.

Utility Relocations

AT&T relocations are ongoing in the Braeburn, Wisterwood and Briar Hollow zones.  Crews have completed placement of new lines in the existing easements, and will be splicing them into the existing system.

 

Tichester and Sherbrooke Zone Residents:

Residents in the construction area have received notifications about the project and a door hanger regarding homeowner items in the right-of-way.  If you wish to preserve these items (custom mailboxes, landscaping, planters, trees, irrigation systems, etc.), it is suggested you begin removing them now from the right-of-way. If homeowner items are not removed by the time construction begins, then the contractor will consider these items left for refuse.

 

Mailboxes: Mailboxes in the path of drainage work will be removed and replaced with standard units. We are in close communication with the post office to ensure there is no disruption of mail service.

 

Driveways: The re-grading of channels and replacement of driveway culverts will require the re-construction of some driveways. Driveways will be accessible by the end of each workday. Full driveway repairs will be made upon completion of the entirety of the work at each property. Notice will be provided to homeowners and residents at least 48 hours prior to any driveway-access interruptions.

 

Irrigation Systems: Irrigation systems in the path of drainage work will be removed, capped at the right-of-way line and will not be replaced.

 

Questions, Subscribe to Email Alerts and Project Webpage

If you have any questions regarding this information, please contact our Public Involvement Team by calling (512) 943-1195 or emailing This e-mail address is being protected from spambots. You need JavaScript enabled to view it .  All project materials and updates, including any lane or road closures, will be posted on the Forest North Drainage Improvement Project page of the Road Bond website.  We encourage you to sign up for news and updates under the "Subscriptions" tab.

 

Forest North Drainage Improvement Project web link: www.roadbond.org/forestnorth

 

Sincerely,

The Williamson County Public Involvement Team

Phone: (512) 943-1195

Email: This e-mail address is being protected from spambots. You need JavaScript enabled to view it

 