Forest North Drainage Project – October 31, 2017 Update

Work in the Bayswater Zone has been completed by Williamson County Road and Bridge. Work in the Anderson Mill Zone is anticipated to start in the fall of 2018

This week DeNucci Constructors, LLC requested substantial completion and has begun working on punch list items.  They have also completed additional seeding in the Bayswater Zone. For the next two weeks, DeNucci Constructors, LLC will complete the punch list items.

All work mentioned above is contingent upon weather conditions.